Your success in Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 Certification exam ensures your professional strength in order to be more successful in future. But you should know the pattern of SAP Project System with SAP ERP 6.0 EHP4 exam to perform well in it. PracticeDumpsGuru provides you latest C_TPLM22_64 practice exam Questions. The SAP C_TPLM22_64 practice exam dumps material consists of two formates, practice test software and pdf files. Practice test software has a user-friendly interface, which helps you to test your preparation and point out your weak areas. Pdf files consists of latest SAP C_TPLM22_64 exam questions.

♥ VALID C_TPLM22_64 Exam Questions 2018 ♥

C_TPLM22_64 exam questions, C_TPLM22_64 PDF dumps; C_TPLM22_64 exam dumps:: https://www.dumpsschool.com/C_TPLM22_64-exam-dumps.html (100 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest SAP C_TPLM22_64 Dumps Exam Questions and Answers:

Version: 5.0
Question: 21

Which account category is used for account assignment of orders, which includes network headers, network activities, maintenance orders, internal orders and manufacturing orders?
Please choose the correct answer.
Response:

A. C
B. B
C. F
D. E

Answer: C

Question: 22

Which of the following statements about milestone billing are correct?
There are 3 correct answers to this question.
Response:

A. The revenue value of the sales order item can be assigned to dates in the billing plan.
B. The amount to be billed is entered directly in the milestones of the WBS elements or activities.
C. The billing block on a billing date is removed when the related milestone is confirmed with an actual date.
D. For each billing date in a billing plan, you can define whether the date is fixed or whether it is moved along with the dates of the milestone.
E. If a milestone is to be used as a date in a billing plan, the “Sales document date” indicator must be activated in the milestone.

Answer: ACD

Question: 23

What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:

A. Cost centers
B. Cost elements
C. Profit centers
D. Profit center hierarchy

Answer: CD

Question: 24

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:

A. Contractual management
B. Claim management
C. Claim Planning
D. Variance management

Answer: B

Question: 25

Which of the following specifies how much time must elapse between individual archiving steps in network type?
Please choose the correct answer.
Response:

A. Functional areas
B. Residence times
C. Classification indicator
D. Functional areas

Answer: B

Question: 26

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:

A. Billing element
B. Cost element
C. Pricing element
D. Account assignment element

Answer: AD